Why are residents concerned?

The proposal is for a large data-centre development close to existing homes. The massive amounts of energy required to power the facility will be supplied by industrial scale on-site gas turbines until grid connection is established which can take up to five years with current backlog.  Residents have raised questions about environmental impacts, infrastructure, transport and whether the submitted assessments fully reflect local conditions.

Summaries below describe issues raised by the campaign. Refer to the application documents and responses from statutory consultees for the underlying evidence and the applicant's position.

The Temporary Energy Centre

The proposed Temporary Energy Centre is expected to operate from approximately July 2028 until 2033 for around five years, until the site is expected to have its full electricity connection.

49.9 MW maximum generating capacity

The Environmental Statement is described as providing for:

  • 7 × PGM70 (Taurus 70) gas turbines, each rated at 8.18 MW
  • 1 × steam turbine/generator
  • 2 × diesel backup generators
  • Maximum generating capacity of 49.9 MW
  • Only 6 of the 7 gas turbines operating at any one time because of the 49.9 MW limit
01 — Nearby homes

Maple Fields and sensitive receptors

Maple Fields is a recently completed residential development approved under application 18/02594/MJR. The submitted material does not consistently treat Maple Fields as a sensitive receptor across the noise, air-quality, lighting, visual, health and cumulative assessments.

The material states that Maple Fields is around 150m from the Temporary Energy Centre, while Ball Lane is identified as the closest representative residential receptor at around 250m.

02 — Noise & air quality

A potential 24-hour industrial operation beside homes

The proposal involves generators, cooling equipment, fans and transformers. Residents are concerned about operational noise, tonal and low-frequency noise, vibration and emissions.

Questions to examine
  • Are all nearby sensitive receptors included in the modelling?
  • Are short-term and long-term pollutant concentrations clearly explained?
  • Are generator testing, maintenance and emergency operating scenarios assessed?
  • Are noise limits and mitigation measures specific, measurable and enforceable?

The original Environmental Statement has been reported in planning documentation as predicting a maximum short-term NO₂ concentration of approximately 194 μg/m³ at a modelled location.

03 — Flood risk

Flood risk and off-site impacts

Planning material raises concerns about flood depths in surrounding areas and questions about blockage scenarios, climate-change allowances and potential off-site effects.

Relevant evidence includes the submitted flood consequences assessment and formal responses from Natural Resources Wales and the local planning authority. NRW have expressed their concerns about flooding and the applicant is yet to remedy these issues.

04 — Lighting & construction

Construction and 24-hour lighting

Residents have raised concerns about security, emergency, road and bridge lighting, glare, light entering homes and gardens, construction traffic and the adequacy of construction management arrangements for the current proposal.

05 — Energy & water

Temporary generation and resource demand

Planning material describes a proposed Temporary Energy Centre intended to provide power while a grid connection is established. The applicant proposes use of industrial methane gas turbines rated up to 49.9MW to power the facility. According to the application these turbines could be in use for up FIVE YEARS and beyond.    

Residents want clarity on the equipment proposed, the expected operating period, emissions, noise, water use and what happens if the grid connection is delayed.

Impact on local communities health

The gas turbines will be located only 130 meters from vulnerable residential areas, which include a foster home for children and housing for elderly and disabled people. Residents near the Colossus data centre in Mississippi (using the same Taurus 70 gas generators) report severe issues including: intense noise, poor air quality, sulfurous smells, coughing, mucus buildup, eye irritation, and breathing difficulties.

Five-mile radius: environmental assessments and reporting note that smog-forming pollutants, nitrogen oxides, and formaldehyde impact communities across a broader five-mile zone.

06 — Scope & certainty

What gets built must stay within what has been assessed

The application includes outline elements and technical details that may be subject to further approval. Residents want the environmental assessment to cover a realistic and sufficiently defined development, with effective controls on plant, layout, emissions, noise and lighting.

07 — Park & Ride

A major transport facility could be lost or reduced

The proposal raises concerns about the existing Park & Ride facility and access to the hospital. Residents want any replacement provision to be clearly identified, funded, consented and available when needed. No suitable replacement has yet been identified.

08 — Third exit bridge

The promised bridge to connect Llanrumney to the A48

A freedom of information request revealed restrictions on vehicular use of the bridge connecting Llanrumney to the A48 - Vehicular use of the bridge shall be restricted to public transport only between the hours of 07:00 and 10:00 and 15:00 and 19:00. No commuters can use the bridge during rush hour and this will be enforced by ANPR cameras.

Using this information: these are summaries of campaign concerns, not a substitute for the planning record or professional advice. Please find the planning documentation on the developers website - www.cardiffeastparkandride.com